Caltrans 55-Hour Weekend Closures

Posted on 06/13/2018

Construction Notice - Caltrans 55-Hour Weekend Closures
 

June through August 2018
San Bernardino Freeway (I-10) 55-hour Road Closures

As part of the bridge rehabilitation project, the California Department of Transportation (Caltrans) will close freeway lanes on East and West bound San Bernardino Freeway (I-10) for 55 hours over ten separate weekends. Underpass and on and off ramps will be closed to accommodate the construction. As bridge deck repairs are conducted, traffic will be diverted. 

Although NOT a full freeway closure, motorists should expect delays and are strongly advised to use alternate routes, avoid the area or use public transit.

Scheduled Closures - Friday 10 p.m. through Monday 5 a.m.

Phase 1:     Atlantic Blvd  June 15 - 18
Phase 2:     Fremont Ave & Sixth St  June 22 - 25
Phase 3:     Garfield Ave & Del Mar Ave                          June 29 - July 2        
Phase 4:     New Ave & Walnut Grove Ave                      July 6 - 9   
Phase 5:     San Gabriel Blvd & Rosemead Blvd             July 13 – 16

Phase 6:     Rosemead Blvd & San Gabriel Blvd             July 20 - 23
Phase 7:     Walnut Grove Ave & New Ave                      July 27 - 30     
Phase 8:     Del Mar Ave & Garfield                                 August 3 - 6
Phase 9:     Sixth St & Fremont Ave                                August 10 - 13
Phase 10:   Atlantic Blvd                                                  August 17 - 20      

Additionally, motorists can check traffic conditions before they leave by calling 511 or visiting the Caltrans Quickmap at quickmap.dot.ca.gov for real time freeway traffic information. Download a copy of the lane closures map here.

Any additional questions regarding freeway construction activities or street closures, please contact Caltrans Public Affairs at (213) 897-3656 or visit www.dot.ca.gov/d7